Skip to main content

Current sensing

A current clamp around the spindle's power supply tells TrackMyMachines when the spindle is cutting. It works on any machine, of any age, without touching the control.

Fit the T-Connect's power first, with the machine still isolated.

Blue split-core current clamp with a black lead ending in a 3.5mm jack plug
The current clamp

Clamp the spindle supply​

  1. Find the spindle's power cables.
Where is the spindle power supply?

In the back of the machine cabinet there's a set of axis amplifiers for all the axes in the machine. The spindle amplifier is often labelled "SP" or "SP1".

  1. Open the clamp and close it around a single phase of the 3-phase spindle supply. One conductor only: clamping two or three phases together cancels the reading out.
  2. Plug the clamp into the 3.5 mm jack labelled 1 on the T-Connect's sensor edge.
  3. If the machine has more productive spindles (for example a multi-tasking machine or a lathe with two spindles), clamp each one the same way and plug them into jacks 2 and 3.
Sensor edge of the T-Connect: four 3.5mm jacks labelled E, 1, 2 and 3, with two status LEDs on the right
The sensor edge: spindle clamps go in 1, 2 and 3, the energy clamp in E

Measure energy (optional)​

If you've opted to measure energy use, clamp one phase of the machine's three-phase main power supply and plug it into the jack labelled E.

Next​

If you're also wiring digital inputs or a machine connection, do that now. Otherwise, close up and check the LEDs — see Finish and check.